Construction Schedule

The following is the site work construction schedule as it stands and it can change depending on upcoming conditions.

May 31st- Exterior Masonry finished

June 1st – Levels 1 and 2 of Garage finished

June 7th – Glass Canopies Installed

July 16th – Level 11 View Lounge and West Podium Lobby finished

July 20th – Level 11 Plaza finished

August 1st – Level 5 Plaza finished


click to enlarge image (pdf)


click to enlarge image (pdf)


Click here to view Live Construction video feed from the project site

Deck Pour Schedule: June 27, 2012- September 6, 2012

Stadium Place Construction Schedule 2012-2014 (pdf)

Stadium Place Noise Measurments: Click to read more

Stadium Place Development – Noise and Vibration Fact sheet: Click to read more